Capital projects pipeline 2026-2031
Summary
City Engineer Brad Holman laid out the full roads picture: 2026 paving done, the Brim Road path finished, Wallace water/sewer nearly complete, and a multi-year pipeline from the Krim-Scott Hamilton path to the North Main shared-use path in 2030-31.
At a glance
- Total mentions
- 6
- Last 30 days
- 1
Rising — discussed at 3 meetings since Sep 28, 2026, up from 0 in the two months before.
Impact analysis
Multiple years of paving, water, sewer and path projects are programmed, several funded through ODOT and Safe Streets for All grants.
Residents on newly paved streets, school kids using new paths, and neighborhoods getting upgraded water and sewer lines.
Mentions & discussions (6)
City Council (Regular) - Oct 19, 2026
City Engineer Brad Holman laid out the full roads picture: 2026 paving done, the Brim Road path finished, Wallace water/sewer nearly complete, and a multi-year pipeline from the Krim-Scott Hamilton path to the North Main shared-use path in 2030-31.
City Council (Regular) - Oct 5, 2026
Brian O'Connell updated council on major utility work: pump stations, the Wallace Avenue water/sewer replacement, wastewater clarifiers, and electric circuit and substation projects across the city.
Board of Public Utilities - Sep 28, 2026
A long list of projects is moving: the low service pump station is nearly done, the membrane expansion design is at 90%, water tower work is heading to bid, and the Manitoba Drive stormwater pump station is now running. These investments keep water and sewer service reliable as the city grows.
Board of Public Utilities - Apr 27, 2026
Deferred capital projects are catching up with the utility: substation transformer replacements, distribution upgrades, and an electric division building. The plan builds spending up from the old $3-3.5 million level to $7 million a year, partly funded with $15 million in borrowings (2027-2029) and cash reserves.
Planning Commission - Mar 4, 2026
The approved list covers new water lines, sewer relining and street paving across the city. Paving on Carr, Ada, Georgia and South Prospect got pushed back because Columbia Gas will be digging those streets up first.
City Council (Regular) - Jan 20, 2026
Mick Murray laid out sidewalk infill, paving, roundabout studies, tree canopy work and facility projects, including a new 50-50 sidewalk replacement program starting this year.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Bowling Green
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.