Council hired GPD Group to design the next phase of repaving on State Route 21 (Brecksville Road). Better pavement is coming, though construction is still downstream.
At a glance
- Total mentions
- 5
- Last 30 days
- 0
Last discussed Sep 1, 2026.
Impact analysis
The design contract amount wasn't stated in the meeting materials.
Drivers who use Brecksville Road daily.
Taxpayers cover the added cost, which Council Member Stucky opposed.
Mentions & discussions (5)
City Council Committees - Sep 1, 2026
Paving on Brecksville Road Phase 2B is done; crews will install loop detectors at the Route 82/21 intersection over about two days with temporary traffic impacts, then finish striping. The fund transfer recommended by the Finance Committee covers the local share of Phase 3.
City Council - Apr 21, 2026
Council added $132,225.20 for construction inspection services on the resurfacing project — the only contested vote of the night.
City Council Committees - Apr 21, 2026
The resurfacing project slipped into 2026, adding a $132,225.20 inspection change order. Council Member Stucky pressed on why the extra cost wasn't discussed months ago, casting the committee's only dissenting vote.
City Council - Mar 17, 2026
Council signed the federal agreement for Phase 3 of Brecksville Road repaving, from State Route 82 to Miller Road, with up to $2.16 million in federal money.
City Council - Feb 3, 2026
Council hired GPD Group to design the next phase of repaving on State Route 21 (Brecksville Road). Better pavement is coming, though construction is still downstream.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Brecksville
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.