Collective bargaining agreement with LIUNA Local 860
The Service Department became a union bargaining unit on July 2, 2026, so the city must reset pay rates to previously agreed levels until negotiations finish — state law bars changing compensation mid-bargaining.
2026 Appropriations and Revenue Adjustments
Council amended the 2026 budget to add $12,100 for HR drug screens, $200,000 to carry Brecksville Road resurfacing engineering into 2026, and about $14,840 for the fire gear dryer (mostly grant-funded).
Employee healthcare, dental and vision insurance contracts
The city renewed its healthcare, dental, and vision insurance plans for employees through Medical Mutual, Delta Dental, and VSP to maintain staff benefits.
Oakes Road Sidewalk Project Wrap-Up
The Safe Routes to Schools sidewalk project from Barr Road to Blossom Hill is moving forward with Allega as the low bidder at $268,808.85; work could start around May and finish before school resumes.
Valor Acres traffic studies
With two to three building sites left, the city is paying TMS Engineers $7,545 to independently verify the developer's traffic study assumptions, focused on Brecksville and Miller Road impacts.
Service Garage fire restoration costs
The city is paying for cleanup and restoration of the Service Garage at 4400 Oakes Road after the April 7 fire, routing $506,979.50 of insurance money to SERVPRO and ratifying the emergency authorization. More construction items may come before Council as work progresses.
Natatorium pool pack replacement funded by $758,000 state grant
The city secured $750,000 in congressional funding toward replacing the 'pool pack' — the bus-sized unit that controls the indoor pool's environment — expected to cost about $1 million. The mayor will propose the project to council, and the natatorium could be closed for several months or even a full season.
Riverview Road culvert project timing
The city is replacing the Riverview Road culvert with cost-sharing from the Northeast Ohio Regional Sewer District and a contractor bid now accepted. Expect construction activity on Riverview Road.