Hampshire Road sewer project change order

Summary

Council added $671,000 to the Fabrizi contract for the Hampshire Road illicit connection controls project, citing design changes and two years of cost inflation. Work started on Mayfield Road and should wrap by spring.

At a glance

Total mentions
1
Last 30 days
1

Discussed at 1 meeting in the last 60 days; most recently Nov 2, 2026.

Impact analysis

💰Financial impact

An added $671,000, mostly covered by ARPA and NOACA grants rather than the general fund.

✅Who benefits