Marion Franklin Pool replacement funding
Summary
The long-delayed pool replacement needs another $1 million after design errors and state permit delays pushed completion four months past deadline — it missed the entire 2026 swim season, with a new completion date of May 28, 2027.
At a glance
- Total mentions
- 2
- Last 30 days
- 2
Discussed at 1 meeting in the last 60 days; most recently Nov 2, 2026.
Impact analysis
$1,009,727 more from the recreation and parks voted bond fund, with the city seeking to recoup $224,000 from the contractor.
Marion Franklin neighborhood residents, who should have a working pool for the 2027 season.
Swimmers who lost the 2026 pool season to the delays, and taxpayers footing the overrun.
Mentions & discussions (2)
Columbus City Council — November 2, 2026
Council added just over $1 million in bond funds to keep the South Side pool replacement on track.
Zoning Committee — November 2, 2026
The long-delayed pool replacement needs another $1 million after design errors and state permit delays pushed completion four months past deadline — it missed the entire 2026 swim season, with a new completion date of May 28, 2027.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Columbus
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.