2026 Street and Sidewalk Maintenance
Summary
Council adopted contracts with Decker Construction for sidewalk lookback and street/sidewalk maintenance work across the city.
At a glance
- Total mentions
- 7
- Last 30 days
- 0
Last discussed Jul 6, 2026.
Impact analysis
Contract costs were not detailed at the meeting.
Residents get repaired sidewalks and streets citywide.
Homeowners displeased with partial driveway apron replacements may still see seams unless they pay to replace the full apron themselves.
Mentions & discussions (7)
Committee of the Whole โ July 6, 2026
Property owners with 2025 sidewalk repairs will see assessments โ payable in full within 30 days of the July 20 hearing or spread over five years with no interest unless paid late. Affected owners were notified June 29.
City Council โ May 4, 2026
Council adopted contracts with Decker Construction for sidewalk lookback and street/sidewalk maintenance work across the city.
City Council โ April 27, 2026
Two ordinances would hire Decker Construction for the year's sidewalk lookback program and street/sidewalk maintenance โ the work that fixes the cracked sidewalks and worn streets residents flag.
City Council โ April 6, 2026
After rejecting low bidders lacking qualifications, the city is recommending Decker Construction for two contracts โ the sidewalk look back program (~$663,000) and street/sidewalk maintenance (~$1.43 million) โ totaling about $2.1 million with inspection costs.
Committee of the Whole โ March 23, 2026
A $585,845 contract with Cap-Stone & Associates will rebuild streets and replace waterlines this year, part of the city's annual infrastructure program.
Property Appeals Board โ February 17, 2026
Three homeowners were scheduled to appeal sidewalk maintenance requirements under Gahanna Code Section 903.4, pitting property owners against city-mandated sidewalk repair obligations. Each case got its own public hearing before the board.
Committee of the Whole โ January 12, 2026
Curb repairs, crack sealing, and micro-resurfacing on selected streets, plus continued sidewalk maintenance on recently rebuilt streets. The city's pavement assessment got delayed to spring 2026, so this year's list stays put. Driveway apron cutbacks remain a sore spot for some homeowners.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Gahanna
What the council decided, in plain English โ one email a week.
Free. Unsubscribe with one click any time. We never sell your email.