Taylor Road Water Main Replacement cost increase
Summary
Construction ran into unexpected utility conflicts, so the engineer of record needs $64,032 more to keep verifying the work. It protects the design intent and public safety.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Aug 17, 2026.
Impact analysis
$64,032.09 extra on top of the original contract.
Residents on Taylor Road get a properly completed, safe water main.
Southern residents and drivers will face temporary traffic disruption during construction.
Mentions & discussions (3)
Committee of the Whole โ August 17, 2026
Construction ran into unexpected utility conflicts, so the engineer of record needs $64,032 more to keep verifying the work. It protects the design intent and public safety.
City Council โ February 2, 2026
Council approved extra money for the Fishbeck design contract so the Taylor Road waterline project also covers new sidewalks. Residents on the north side of Taylor Road will get waterline work plus 5-foot ADA-compliant sidewalks replacing older 4-foot ones.
City Council โ January 2, 2026
The city hired Shelly & Sands to replace the Taylor Road water main. Councilmember Bowers warned it will likely disrupt traffic and residents in the southern part of town.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Gahanna
What the council decided, in plain English โ one email a week.
Free. Unsubscribe with one click any time. We never sell your email.