Data center development standards
Summary
A resident raised concerns about data centers at the transportation committee meeting; the mayor and planning director said the city is looking at possibly instituting a moratorium on data centers in Green.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 22, 2026.
Impact analysis
No direct cost now; data centers generate high property valuation but few permanent jobs, per staff.
Residents worried about data center impacts if a moratorium is adopted.
None directly yet; public perception of data centers is negative, and council could face pushback for not banning them outright.
Mentions & discussions (3)
Committee Meetings - Sep 22, 2026
The administration has drafted preliminary rules for data centers, with size restrictions and added study requirements for large facilities. Planning and zoning is reviewing it, and formal legislation is expected in coming months.
Planning and Zoning Commission - Sep 16, 2026
The city has no rules for data centers, which are drawing regional attention for their power and water demands. The draft would tier review by size — conditional up to 30,000 sq ft, extra scrutiny to 70,000, larger projects prohibited outright. Most likely locations would be near the airport's industrial area and its electrical grid.
City Council - Apr 28, 2026
A resident raised concerns about data centers at the transportation committee meeting; the mayor and planning director said the city is looking at possibly instituting a moratorium on data centers in Green.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Green
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.