Graybill Road turn lane change orders
Summary
The turn lane project at Green Elementary ran about $58,600 over the original bid — mostly because two sewer manholes needed far more work than expected. Council has to sign off since the increase blew past the 10% limit.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Feb 10, 2026.
Impact analysis
Adds $58,594.17 to a contract that was originally about $191,153.
Families and drivers around Green Elementary once the turn lane is finished.
Mentions & discussions (2)
City Council - Feb 10, 2026
The turn lane project at Green Elementary grew about 22% because contractors had to adjust two sanitary manholes deeper than planned — the final cost is now $249,747.10 versus the original $191,152.93.
Committee Meetings - Feb 10, 2026
The turn lane project at Green Elementary ran about $58,600 over the original bid — mostly because two sewer manholes needed far more work than expected. Council has to sign off since the increase blew past the 10% limit.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Green
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.