Council gave final approval to next year's capital budget — the big-ticket items include $6.2 million for street repaving, $1.75 million for sidewalks, $4.8 million for the Heritage Trail Extension, and major water and sewer work.
At a glance
- Total mentions
- 3
- Last 30 days
- 3
Discussed at 2 meetings in the last 60 days; most recently Nov 9, 2026.
Impact analysis
The capital budget is balanced; the Heritage Trail Extension's $4.8 million city cost is offset by an $8.7 million state grant and cost-sharing through the TSI program reimbursed through 2031.
All Hilliard residents benefit from maintained roads, sidewalks, trails, water, and sewer systems.
Mentions & discussions (3)
City Council - Nov 09 2026
The final capital budget presentations cover parks maintenance (pool deck, paths, signage, equipment) and police needs (cruisers, vests, weapons, radios). The path project at Municipal Park and the Athletic Complex tops $1 million with roughly $600,000 in potential state reimbursements.
Committee of the Whole - Nov 09 2026
Council gave final approval to next year's capital budget — the big-ticket items include $6.2 million for street repaving, $1.75 million for sidewalks, $4.8 million for the Heritage Trail Extension, and major water and sewer work.
City Council - Oct 26 2026
Council got its first look at a roughly $33.9 million 2027 capital budget. About $5 million should come back in grants. Full department presentations were pushed to the next committee-of-the-whole meeting, with a second reading November 9.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Hilliard
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.