HighWater Utilities

Stormwater, creek alignment and sewer capacity concerns

Residents dispute the mapped path of Middle Branch Henry Creek, report recurring sewage backups from the Costner pump station, and fear new impervious surfaces will worsen flooding. Staff said detailed surveys come only at the detailed development plan stage.

1 mention (1 this month)Last discussed Nov 10, 2026
HighWater Utilities↑Rising

Water Billing Software Transition

The utility billing system is switching over and offices are closed November 4-13. If you use AutoPay, you must re-enroll with your new account number — but no late fees or shutoffs through January 2.

5 mentions (4 this month)Last discussed Nov 9, 2026
HighWater Utilities

Sewer lift station capacity in Carriage Trails

A resident warned the existing Carriage Trails lift station may be near capacity with apartments and hundreds of new homes coming. Staff explained the next lift station is designed, developer-funded (~$1 million), and timed to come online in late 2028/early 2029, with connections capped at 300 homes until then.

4 mentions (2 this month)Last discussed Oct 28, 2026
LowWater Utilities

Citizens Water and Sewer Advisory Board appointment

Hunter Stover is recommended to fill the last vacancy on the board that advises the city on water and sewer matters, bringing it to full membership.

5 mentionsLast discussed Oct 12, 2026
MediumWater Utilities

New production well connection at Rip Rap Road

A new municipal water well gets its pump, meter vault, and connection to the water system for up to $1.225 million — part of the city's ongoing water infrastructure overhaul.

2 mentionsLast discussed Sep 8, 2026
MediumWater Utilities

Sanitary sewer rehabilitation program

The city will line 8,000-9,000 feet of cracked or collapsing sewer pipe, its eighth year running this program, paid from sewer fees.

3 mentionsLast discussed Aug 10, 2026
MediumWater Utilities

Bridgewater Road water main extension

Council approved a contract to extend the water main on Bridgewater Road, funded through the water fund.

1 mentionLast discussed Aug 10, 2026
HighWater Utilities

2026 Sewer and Water Infrastructure Projects

Council greenlit three utility projects: rehabilitating sewer lines, replacing filter media at the Rip Rap Road water plant, and building a new Brandt Pike lift station that combines two aging ones. These keep water and sewer service reliable as the city grows.

3 mentionsLast discussed Jul 20, 2026
HighWater Utilities

Tri-Cities $223.8 Million Plant Overhaul

Main breaks are down this year (29 vs. 39 last year), but hard water deposits from the new membrane setup may be causing some breaks — expected to be temporary.

2 mentionsLast discussed Jul 20, 2026
HighWater Utilities

Water bill relief fund

The city is rewriting its water leak adjustment policy, which decides who gets a credit on a big bill after a leak. The board wants to know if the change will also cover sewer adjustments, and the new policy will be posted on the city website once finished.

2 mentionsLast discussed Jul 20, 2026
MediumWater Utilities

New sanitary lift station near Walmart

Two aging sewer lift stations near Walmart will be replaced with one new station under a contract with Outdoor Enterprise, LLC, the lowest and best bidder.

1 mentionLast discussed Jun 8, 2026
LowWater Utilities

Faster EV chargers at Rose Music Center

The city is pursuing federal RIDES grant money to swap the Level 2 chargers at the Rose Music Center for faster Level 3 units — about $55,000 each to install — and move the old chargers to other city facilities for fleet use.

1 mentionLast discussed Jun 8, 2026
MediumWater Utilities

Brandt Pike lift station replacement

Two 1960s-era lift stations near Walmart will be replaced by one modern station, with a $1.44 million bid from Outdoor Enterprises. The new station is sized for future growth along the corridor.

2 mentionsLast discussed Jun 2, 2026