Council added $127,884 to the Downtown Pedestrian Phase 2 project, funding curb ramps, new sidewalk on South Main Street between Bard and Stoney Hill, and upgraded pedestrian signals along SR 91 and SR 303.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Apr 28, 2026.
Impact analysis
Adds $127,884.34 to the project budget.
Pedestrians, including residents like commenter Steven Foskett who walk along SR 91 daily.
Mentions & discussions (3)
City Council (Work) - Apr 28, 2026
The city is fixing crosswalks, driveways and turn lanes on West Streetsboro Street this summer, with a bigger underpass widening project possible next year if a storage facility owner cooperates. Residents near the corridor should see safer pedestrian and traffic conditions.
City Council - Feb 3, 2026
Council added $127,884 to the Downtown Pedestrian Phase 2 project, funding curb ramps, new sidewalk on South Main Street between Bard and Stoney Hill, and upgraded pedestrian signals along SR 91 and SR 303.
City Council (Work) - Jan 27, 2026
The downtown pedestrian project — new sidewalks on South Main Street, crosswalk and signal upgrades — came in at its bid estimate, but the earlier budget was too low, so staff is asking for a $127,884 increase.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Hudson
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.