Velocity Broadband residential expansion
Summary
Council authorized bidding for year two of the fiber-to-the-home build and approved upgraded Calix customer-support software for Velocity. A resident praised the city-run broadband service's customer service and urged continued expansion.
At a glance
- Total mentions
- 13
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 6, 2026.
Impact analysis
Year-two construction will be awarded to the lowest and best bidder; the Calix contract amount was not stated.
Hudson households and businesses gaining access to the city's fiber network.
Residents dealing with utility disruptions, backups, and construction traffic during the installs.
Mentions & discussions (13)
City Council - Oct 6, 2026
Council greenlit bidding for construction of the second phase of the city's residential fiber internet buildout, combining areas from the cancelled earlier contracts under updated safety specs.
City Council - Sep 15, 2026
A $15M note ordinance for expanding residential broadband had its first reading; staff is also publishing a new neighborhood-by-neighborhood construction map and updated timeline.
City Council - Jun 16, 2026
Council was scheduled to consider an amended contract with Cogent Communications that adds a monthly fee for redundancy on the city's Velocity Broadband network — likely to keep the service more reliable.
City Council (Work) - Jun 9, 2026
Ward 4 residents met with the city engineer over ongoing frustrations with fiber installs — gas line breaks, traffic and visibility concerns, and one sewer lateral hit. City officials pledged better communication, work zone safety measures, and lessons learned going forward.
City Council - Jun 2, 2026
Velocity Broadband renewed its Zayo internet backbone for three years and got bandwidth bumped to 10 Gbps, plus a $300,000 purchasing cap for 2026 operations.
City Council (Work) - May 26, 2026
The annual update showed a near-50% take rate in the pilot, new construction tracking dashboard, material cost inflation and 44-week lead times, and emerging overlap with Windstream/Kinetic builds that could change which neighborhoods get city fiber.
City Council - Apr 7, 2026
The city extended its engineering contract with Iron Claw Engineering by up to $250,000 to keep the fiber-to-the-home project on track, locking in current rates after a first year completed under budget.
City Council - Mar 17, 2026
A $266,000 bulk modem buy from Calix keeps Velocity Broadband subscribers supplied; Weinstein sat out the vote over a conflict of interest.
City Council (Work) - Mar 10, 2026
A $266,000 modem purchase for Velocity Broadband subscribers was moved to legislation after Weinstein disclosed a conflict. Staff wants fast approval because new equipment takes 8–10 weeks to arrive ahead of the fiber-to-the-home push.
City Council - Feb 17, 2026
Four resolutions clear the way for up to $3.5 million in contracts to build aerial and underground fiber and install customer equipment across north, central, and south Hudson.
City Council - Feb 3, 2026
Council authorized bidding for year two of the fiber-to-the-home build and approved upgraded Calix customer-support software for Velocity. A resident praised the city-run broadband service's customer service and urged continued expansion.
City Council (Work) - Jan 27, 2026
The city would advertise bids and contract for the second year of Velocity Broadband fiber construction (July 2026–June 2027).
City Council (Work) - Jan 17, 2026
The city is planning a 4-year fiber internet buildout and weighing whether speeding it to 3.5 years is worth the tradeoffs.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Hudson
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.