The county opened five bids to rebuild Danville's water mains, valves, and hydrants, funded by a $300,000 CDBG grant plus $200,000 from the revolving loan fund. The low bid of $466,121 from Driven Excavating is just under the $470,000 estimate — an award is expected within about a week.

At a glance

Total mentions
6
Last 30 days
0

Last discussed Sep 15, 2026.

Impact analysis

💰Financial impact

About $500,000 total, mostly grant-funded — the low bid comes in slightly under the engineer's estimate.

✅Who benefits

Danville residents get modernized water infrastructure with upgraded mains, valves, and hydrants.

⚠️Who could be affected

Residents may see continued water-loss-driven strain on supply until the leak source is found.

Mentions & discussions (6)

MeetingSep 15, 2026approved

Board of Commissioners — September 15, 2026

The county signed off on a $466,121 contract with Driven Excavating to upgrade the Village of Danville's water system, paid for through a CDBG grant.

MeetingSep 1, 2026

Board of Commissioners — September 1, 2026

Danville's water system is getting a $466,121 upgrade through the federal CDBG program, with Driven Excavating doing the work slightly under estimate. Residents should see improved water infrastructure without a local funding hit.

MeetingAug 13, 2026

Board of Commissioners — August 13, 2026

The county opened five bids to rebuild Danville's water mains, valves, and hydrants, funded by a $300,000 CDBG grant plus $200,000 from the revolving loan fund. The low bid of $466,121 from Driven Excavating is just under the $470,000 estimate — an award is expected within about a week.

MeetingJun 30, 2026

Board of Commissioners — June 30, 2026

The county is advertising for contractors to bid on Danville's water system upgrades, backed by up to $470,000 in CDBG grant funds.

MeetingApr 2, 2026

Board of Commissioners — April 2, 2026

The county published notice of federal funding release for Danville's critical water system upgrade, a roughly $470,000 project.

MeetingMar 17, 2026

Board of Commissioners — March 17, 2026

Water and Wastewater is hunting a 40% water loss, likely frozen meters, while pushing forward on Well #7, a new Apple Valley admin building, and sewer fixes. The new well should ease summer supply worries.

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Knox County

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.