Board of Commissioners — October 29, 2026
The county transit facility probably won't open by Thanksgiving — fire suppression requirements, elevator installation, and unfinished Land Bank roadwork pushed the guess to between Thanksgiving and Christmas.
Board of Commissioners — September 29, 2026
The new transit building is in finishing stages — drywall up, walls painted, bathroom tile being installed, with two lifts going into the garage and two new buses expected at the end of October.
Board of Commissioners — July 28, 2026
The new Knox County Transit building is coming along — drywall nearly done, elevator shaft up, and Modern Builders still targeting completion around Thanksgiving. The location is more walkable and accessible than the current spot.
Board of Commissioners — April 28, 2026
Construction on the new Knox County Transit building is moving along well, with the latest walk-through finding no issues.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Knox County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.