High PriorityWater Utilitiesopen

Water and Wastewater and Transit Building Projects

Summary

The new transit building is moving fast — Modern Builders is at work, with walkthroughs underway and ADA ramp and elevator details being worked out. Downtown crosswalk projects should wrap up in the coming weeks.

At a glance

Total mentions
7
Last 30 days
2

Rising — discussed at 3 meetings since Sep 24, 2026, up from 1 in the two months before.

Impact analysis

💰Financial impact

The elevator project's cost isn't known yet, and officials hope to avoid roof work to keep 2027 capital spending limited to the elevator and morgue projects.

✅Who benefits

Transit riders and pedestrians downtown.

⚠️Who could be affected

Visitors to the 117 E. High Street building face parking closures Monday.

Mentions & discussions (7)

MeetingNov 10, 2026

Board of Commissioners — November 10, 2026

The transit and operations center should be done by year's end once a fire alarm panel issue clears with the state. The water/wastewater office move is weeks away, and the courthouse elevator replacement is targeted for 2027, reusing the existing shaft to preserve the historic space.

MeetingNov 3, 2026

Board of Commissioners — November 3, 2026

The new water and sewer building near Apple Valley is close to done — asphalt this week, completion targeted for end of November. The transit building is delayed by state fire suppression permitting.

MeetingSep 24, 2026

Board of Commissioners — September 24, 2026

Two building projects — the new Water and Wastewater office and the transit center — are both aiming for Thanksgiving completion. The courthouse elevator update will be costly and must be bid, and the transit parking lot gets only a base asphalt layer this year.

MeetingAug 4, 2026

Board of Commissioners — August 4, 2026

Construction on the new water and wastewater admin building starts within about three weeks, targeting completion by year's end; the new transit building is on track for late October/early November.

MeetingApr 28, 2026

Board of Commissioners — April 28, 2026

The county is retiring the $2.5 million note it took out a year ago for the transit/county business center building, saving interest on a rolling note.

MeetingApr 16, 2026

Board of Commissioners — April 16, 2026

Crosswalk work on High and Chestnut Streets is nearly done, with the handicap parking lot closed Monday while the city relocates flashing beacons. The new Knox County Transit building continues on schedule with a few design changes.

MeetingApr 7, 2026

Board of Commissioners — April 7, 2026

The new transit building is moving fast — Modern Builders is at work, with walkthroughs underway and ADA ramp and elevator details being worked out. Downtown crosswalk projects should wrap up in the coming weeks.

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Knox County

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.