HighRoads

Ety Road, Memorial Drive & Michaels Way Financing

Two ordinances would let the city borrow roughly $650,000 total — a $495,741.20 revenue note and a $153,799.75 note reimbursing Flagstar Bank — to cover remaining costs of the road improvements. Both are on third reading.

1 mention (1 this month)Last discussed Nov 9, 2026
HighRoads

Sixth Avenue Bridge delay

The project must be rebid after the only bid came in more than 20% above the $2.4 million estimate; the city hopes raising the estimate to about $2.55 million will draw more competitive bids.

2 mentionsLast discussed Sep 14, 2026
HighRoads

East Main Street shoulder widening and sidewalk project

The city is spending $335,000 total on land acquisition for the East Main Street walkways, 90 percent federally reimbursed — but the property owners along the route don't want to sell, and Knisley warned eminent domain could be used.

2 mentionsLast discussed Aug 24, 2026
HighRoads

Arbor Valley Drive and 6th Avenue bridge progress

Council passed funding using school district contributions and street levy funds for this road project.

4 mentionsLast discussed Aug 24, 2026
HighRoads

Chestnut Street one-way conversion

Chestnut Street between High and Columbus becomes one-way westbound June 3. It fixes the narrow-street parking hazards, creates a three-way stop at High and Chestnut, and adds about 20 downtown parking spaces. Residents who've lost cars to crashes there strongly support it.

4 mentionsLast discussed May 4, 2026
HighRoads

Whiley Road reconstruction

The city can now sign agreements with Fairfield County and hire consultants, bid the work, and award a construction contract for rebuilding Whiley Road.

1 mentionLast discussed Jan 12, 2026