8 issues in roads
Memorial-Pierce Walk Ways Project
First reading of legislation to accept federal aid grant funds, advertise bids, and hire an inspection consultant for the Memorial-Pierce walk ways construction.
Ety Road, Memorial Drive & Michaels Way Financing
Two ordinances would let the city borrow roughly $650,000 total — a $495,741.20 revenue note and a $153,799.75 note reimbursing Flagstar Bank — to cover remaining costs of the road improvements. Both are on third reading.
Fifth Avenue Improvement Grant
The city will apply for an Ohio Public Works Commission grant to pave Fifth Avenue in 2028, with the resolution rushed through on suspension to beat the deadline.
River Valley Boulevard intersection repaved
After residents complained about vehicle damage at the Whittier/River Valley four-way stop, Council Member Sollie and code enforcement got the mall to repave the deteriorated intersection.
Sixth Avenue Bridge delay
The project must be rebid after the only bid came in more than 20% above the $2.4 million estimate; the city hopes raising the estimate to about $2.55 million will draw more competitive bids.
East Main Street shoulder widening and sidewalk project
The city is spending $335,000 total on land acquisition for the East Main Street walkways, 90 percent federally reimbursed — but the property owners along the route don't want to sell, and Knisley warned eminent domain could be used.
Arbor Valley Drive and 6th Avenue bridge progress
Council passed funding using school district contributions and street levy funds for this road project.
Transit EV study MOU with the county
Since transit moved to the county, a state EV study grant stays in the city's name — the county will do the study and spend the money, with reimbursements routed through the city back to the county.