The Cincinnati/Glosser roundabout was expected to open the morning after the meeting, about two weeks early; the south leg has a design error to fix.
At a glance
- Total mentions
- 4
- Last 30 days
- 0
Last discussed Sep 8, 2026.
Impact analysis
Grant-funded if awarded; local share not yet determined.
Commuters who've been detoured around the closed intersection.
Mentions & discussions (4)
City Council โ Council Meeting โ 2026-09-08
Work on Glosser Road is back on after weeks of delay caused by a scheduled Duke Energy transmission outage, with completion expected in about three weeks.
City Council โ Council Meeting โ 2026-07-14
The Cincinnati/Glosser roundabout was expected to open the morning after the meeting, about two weeks early; the south leg has a design error to fix.
City Council โ Council Meeting โ 2026-06-09
Construction on the Cincinnati Lebanon Road/Glosser Road roundabout is about two weeks ahead of schedule, with paving starting soon and multiple crews working daily.
City Council โ Council Meeting โ 2026-05-26
The city will apply for an OKI STBG grant to help build a roundabout at Columbus Avenue and Miller Road, aligned with the Safe Streets plan, with design in 2028 and construction around 2030.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Lebanon
What the council decided, in plain English โ one email a week.
Free. Unsubscribe with one click any time. We never sell your email.