Summary

A $1.99 million project rebuilding Suncrest Lane and Meadow Drive — storm sewers, water mains, sanitary sewer work through Colonial Park West, new curbs, pavement, and sidewalks. A state grant is helping pay for it, and work starts in July.

At a glance

Total mentions
1
Last 30 days
0

Last discussed May 12, 2026.

Impact analysis

💰Financial impact

$1,987,618.81 contract, offset in part by a state Public Works grant.

✅Who benefits

Neighbors on Suncrest and Meadow Lane get new streets, sidewalks, and modern underground utilities.