Center Ridge Road widening overage invoice
Summary
ODOT billed the city about $3.6 million in engineering and contractor overages on the Center Ridge widening — mostly blamed on Windstream's slow utility moves. ODOT is holding $2.7 million in escrow and wants another $923,000, and the city plans to fight it, possibly in court.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 21, 2026.
Impact analysis
Could cost taxpayers up to $923,000 more on top of $2.7 million already held, with litigation likely.
Potentially city taxpayers if the city successfully shifts the overage costs to Windstream or ODOT.
Residents could be saddled with the debt if the city loses the dispute.
Mentions & discussions (1)
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for North Ridgeville
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.