MLK Park restroom facility cost increase

Summary

The new public restroom at Martin Luther King Jr. Memorial Park came in over budget, mainly due to a street repair done before paving; Council raised the contract cap to $542,410.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Sep 1, 2026.

Impact analysis

💰Financial impact

Contract total rose from an initial 5% contingency to as much as 10%, up to $542,410.

✅Who benefits

Farmers market visitors, park users and downtown events.