Municipal buildings project locked in under budget
Summary
Two bond packages — $21M for the E. River Road building and $8M for city hall and police building improvements — got second readings; final votes March 17.
At a glance
- Total mentions
- 7
- Last 30 days
- 2
Rising — discussed at 3 meetings since Oct 12, 2026, up from 0 in the two months before.
Impact analysis
$29 million total in bond debt for the two building projects.
City operations housed in the River Road, municipal, and police buildings.
Taxpayers, who will service the bond debt.
Mentions & discussions (7)
Perrysburg offices to relocate during municipal building remodeling
Perrysburg offices to relocate during municipal building remodeling WTOL
City Council - Oct 20, 2026
Council locked in a guaranteed maximum price of just under $14.6 million with Rudolph/Libbe for the new municipal buildings — about $2 million under budget. Construction on the River Road building starts in December and the municipal building in January; meetings move to the Schaller Building next year.
Finance Committee - Oct 13, 2026
The Rudolph Libbe guaranteed maximum price of just under $14.6 million for city building renovations comes in about $2 million under budget, with a 10% contingency included.
Service Committee - Oct 12, 2026
The Rudolph Libbe guaranteed maximum price for renovating the Municipal Building, police building, and River Road building came in $2 million under budget. Construction starts in December, and meetings move to the Schaller Building next year.
Finance Committee - May 12, 2026
Budget amendments all tie to the Municipal Facilities Project, and the city may lease temporary office space — the Arbor Building and Township building — while work is underway.
City Council - Mar 17, 2026
Council approved two bond ordinances totaling up to $29 million — one to finish the East River Road building purchase and renovation, one for the municipal and police buildings. The emergency passage lets the city retire $4 million in short-term notes due May 1.
City Council - Mar 3, 2026
Two bond packages — $21M for the E. River Road building and $8M for city hall and police building improvements — got second readings; final votes March 17.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Perrysburg
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.