Wastewater plant primary clarification expansion
Summary
A new 66-foot primary clarifier tank, a duplicate of the existing one, will add about 6.3 million gallons of treatment capacity at the wastewater plant.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jul 27, 2026.
Impact analysis
Design services cost up to $484,500; construction to follow later.
All sewer users citywide, as the plant prepares for future growth.