Watermain replacement on Front, Second, Third and Indiana
Summary
The city is replacing waterlines on several near-downtown streets using directional drilling where possible to save trees, sidewalks, and driveways. The low bid came in under the $3.5M budget.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 6, 2026.
Impact analysis
About $3.33 million with contingency, under the $3.5 million budgeted.
Residents on those streets get upgraded waterlines with less neighborhood disruption.
Hillebrand & Sons Construction, which submitted the apparent low bid, loses the award and argues the premium isn't the best value for taxpayers.
Mentions & discussions (3)
City Council - Oct 6, 2026
Council reauthorized the state revolving loan agreement for the watermain replacement so the project can proceed.
City Council - Aug 4, 2026
A $3.3 million project will replace water mains using directional drilling — boring under yards instead of open-trenching — to spare trees, driveways and sidewalks. The low bidder complained the award costs $862,082 more than his bid; council weighed the trade-off and approved it anyway.
Public Utilities Committee - Jul 27, 2026
The city is replacing waterlines on several near-downtown streets using directional drilling where possible to save trees, sidewalks, and driveways. The low bid came in under the $3.5M budget.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Perrysburg
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.