Lomond/Lynnfield SSO-11 sewer project and Lomond Boulevard oak trees
Summary
The project to stop sewer overflows and basement backups hit a snag: auger boring failed in tough soil conditions, forcing a $5 million redesign. Council must pick between four options ranging from a $2.4 million contract increase to walking away entirely.
At a glance
- Total mentions
- 8
- Last 30 days
- 0
Last discussed Aug 17, 2026.
Impact analysis
Original contract was $8.3 million; the redesign has cost $5 million, and the roadway open-cut option would raise the contract to about $10.7 million.
Residents of the Lynnfield/Lomond sewer-shed, who would finally see an end to sanitary sewer overflows and basement backup risk.
Taxpayers citywide bear the added costs, and Lomond Boulevard residents face street excavation if the open-cut roadway option is chosen.
Mentions & discussions (8)
Shaker Heights regains environmental exemption for sewer project, tree removal
Shaker Heights regains environmental exemption for sewer project, tree removal Cleveland.com
Finance Committee - Aug 17, 2026
The city signed off on the paperwork to reimburse the $2 million zero-interest state loan for the sewer overflow control project wrapping up in spring 2027.
Safety & Public Works Committee - Aug 6, 2026
The $8.3 million sewer project serving 1,200+ homes hit unexpected construction challenges — dewatering must finish before pipe work can proceed, and the city is awaiting Ohio EPA approval of modified installation methods. Progress is slower than hoped but moving in a positive direction.
City Council (Regular) - Jul 27, 2026
Residents with a 559-signature petition blasted the sewer project: unsafe trenches, damaged trees, a dewatering plan that may kill nine legacy oaks, and poor communication. Some asked the City to seek an EPA extension until the trees go dormant in late fall.
City Council (Work) - Jul 21, 2026
The city has to replace a sanitary sewer along Lomond Boulevard, but the line runs straight through the root zones of nine mature oaks. The state forester says most are already declining and recommends removing them before construction to avoid tree failure and Oak Wilt spreading to nearby oaks.
City Council (Work) - Jul 7, 2026
The Lynnfield/Lomond SSO project addresses sanitary sewer overflows in those neighborhoods, which can cause backups during heavy rain. Council received a status update from Public Works staff, but took no action.
City Council (Regular) - May 26, 2026
A resident on the Lomond/Winchell corner says the sewer project left a pit in her yard for months, abandoned pumps, and no lawn restoration — and she's worried about losing tree lawns next. She's asking for better communication.
City Council (Work) - May 5, 2026
The project to stop sewer overflows and basement backups hit a snag: auger boring failed in tough soil conditions, forcing a $5 million redesign. Council must pick between four options ranging from a $2.4 million contract increase to walking away entirely.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Shaker Heights
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.