Top issues during term (7)(Roads)
2026 street resurfacing program
$1.896 million contract, about $104,000 under the engineer's estimate.
East Central Avenue resurfacing
About $382,000 of the roughly $1.08 million project comes from the city.
Traffic signal radar detection upgrades
Contract cost not stated; program began with a $400,000 state safety grant.
Wright Station parking lot paving
Costs the city $85,867.
Weidner Road access to high school campus
The city has spent $964,000 over five years on nearby school-traffic improvements.
Storm Flooding Impacts
Yankee Road Roundabout Design
Design and engineering contract of $227,904; construction costs come later.
Decisions during term (0)
Recorded while Chmiel was in office — not necessarily decisions they moved, spoke to, or voted on.
No decisions found matching Roads.
Voting record (0)(Roads)
No votes found matching Roads.