The AMP amphitheater budget overage
Summary
The AMP is tracking about $157,000 over budget for 2026, though not over the overall project cost. The city received $50,000 in state funding, the mayor is organizing a naming-rights fundraising campaign, and federal funding is still pending. Council Member Coffey asked for quarterly updates.
At a glance
- Total mentions
- 4
- Last 30 days
- 0
Last discussed Jun 18, 2026.
Impact analysis
About $157,000 over budget for this year, with fundraising and grants expected to keep the overall project near plan.
Residents get the amphitheater project kept near its planned cost.
Mentions & discussions (4)
Finance Committee - Jun 18, 2026
The AMP is tracking about $157,000 over budget for 2026, though not over the overall project cost. The city received $50,000 in state funding, the mayor is organizing a naming-rights fundraising campaign, and federal funding is still pending. Council Member Coffey asked for quarterly updates.
Parks & Recreation Board (Regular) - Apr 13, 2026
The amphitheater broke ground April 12, and the city aims to raise about $1.1 million in sponsorships to pay for the bike trail spur — keeping the whole project debt-free. Only four sponsorship packages are offered, deliberately kept limited to avoid a billboard look.
City Council - Apr 9, 2026
Council approved two no-bid design contracts for the AMP, and the city breaks ground this Sunday. Two grant applications are still pending that could offset costs.
Public Improvements Committee - Apr 9, 2026
The amphitheater project is moving from design to build, with construction starting Monday, April 13 after a rain delay. Two contracts keep the architects involved through construction and advance a bike trail spur connecting to the Hike and Bike path.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Stow
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.