The AMP construction and design contracts
Summary
The amphitheater project is moving from design to build, with construction starting Monday, April 13 after a rain delay. Two contracts keep the architects involved through construction and advance a bike trail spur connecting to the Hike and Bike path.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Apr 9, 2026.
Impact analysis
The two contracts together total $131,500 from the capital fund.
Residents get a new amphitheater and a bike-friendly trail connection sooner.
Mentions & discussions (3)
Public Improvements Committee - Apr 9, 2026
The amphitheater project is moving from design to build, with construction starting Monday, April 13 after a rain delay. Two contracts keep the architects involved through construction and advance a bike trail spur connecting to the Hike and Bike path.
City Council - Apr 9, 2026
Council approved two no-bid design contracts for the AMP, and the city breaks ground this Sunday. Two grant applications are still pending that could offset costs.
City Council - Mar 12, 2026
The mayor reported dirt moves March 30 with a public pop-up event April 12, and the city committed to 100+ programming events annually for the amphitheater development.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Stow
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.