Road and signal construction updates

Good news on commute corridors: the Kent Road signal project finished a month early and under budget, Liberty Road's waterline wraps up soon, and the smart signals on Routes 59 and 91 should start talking to each other within a month or two — easing the congestion residents complain about.

1 mentionLast discussed Jul 9, 2026
MediumRoads

2026 capital projects — sidewalks, Young Road, cemetery

The capital plan shows road projects moving ahead; Young Road's east-side sidewalk will be done within about a month. The Young Road Cemetery project carries a $1.2 million price tag split over two years, and the Progress Park erosion project was scrapped after a homeowner refused to sign off.

1 mentionLast discussed Jun 18, 2026
MediumRoads

Sidewalk damage from street trees

Members discussed how tree roots heave sidewalks and whether concrete leveling instead of full replacement could save money, though roots often re-heave new slabs. The fall walk-and-talk with council is meant to surface these concerns directly.

1 mentionLast discussed Apr 13, 2026
MediumRoads

Routes 91 and 59 Construction

Construction is ramped up on the city's two major road projects, mostly south of Graham Road where the corridor is tight. Officials are asking drivers to slow down and be patient through the work zones.

1 mentionLast discussed Mar 12, 2026
MediumRoads

LED lighting upgrade at Route 8/Steels Corners interchange

Swapping six halogen bulbs for LEDs across four light units should slash maintenance, since each pole takes half a day to lower and raise for a bulb change. The state's reconstruction project didn't cover it.

1 mentionLast discussed Mar 12, 2026
MediumRoads

Route 59/Kent Road traffic signals

$650,000 in notes will fund new traffic signals and ADA-compliant equipment on Route 59 between Sycamore Drive and Fishcreek Road.

1 mentionLast discussed Mar 12, 2026
MediumRoads

Salting operations and cul-de-sac icing

Service Director Nick Wren reported salt deliveries are delayed statewide and cul-de-sacs remain icy because low traffic won't activate the salt — the city has about 2,700 tons on hand for the next storms.

1 mentionLast discussed Feb 12, 2026
MediumRoads

Winter road salt supply

Service Director Nick Wren reported salt deliveries are delayed statewide and cul-de-sacs remain icy because low traffic won't activate the salt — the city has about 2,700 tons on hand for the next storms.

2 mentionsLast discussed Feb 12, 2026
MediumRoads

Route 8 guardrail replacement

Lake Erie Construction will replace guardrail and posts along Route 8, with most costs covered by insurance. Feldman pushed to see Stow's own guardrail repairs scheduled soon.