Downtown Transportation Improvements Phase 2
Summary
Council closed out Phase 1 change orders and hired a construction manager for Phase 2, keeping the multi-million-dollar downtown rebuild on track with a final change order expected this spring.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Mar 16, 2026.
Impact analysis
Phase 1 change order adds just $162.75; Phase 2 construction management is capped at $244,764.
Downtown businesses, drivers, and pedestrians who use the improved streets.
Downtown businesses and drivers will face southbound detours during construction, though one northbound lane stays open.
Mentions & discussions (2)
City Council Video — 2026-03-16
Construction on Main Street between Maplewood and Erie is estimated at $5.28 million, half covered by state grant/loan funds. Expect northbound traffic maintained and southbound detoured; work could start in July and wrap up by Memorial Day 2027.
City Council Video — 2026-02-17
Council closed out Phase 1 change orders and hired a construction manager for Phase 2, keeping the multi-million-dollar downtown rebuild on track with a final change order expected this spring.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Sylvania
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.