7 issues in roads with medium priority

MediumRoads

Monroe/Main/Summit traffic signal upgrades close

The pedestrian beacon project goes to construction at $551,598.80 — a bid nearly 25% under estimate — with 90% paid by federal safety funds.

3 mentions (1 this month)Last discussed Nov 2, 2026
MediumRoads

Convent Blvd./Little Rd. resurfacing closes under budget

Sylvania joined a joint resurfacing project with the township and county covering Jamesford Woods, Spring Forest and other subdivision roads plus the Sylvania/McCord intersection — $2.41 million total, with the city's $140,010 share due in 2029 and state grant money offsetting it.

3 mentions (1 this month)Last discussed Nov 2, 2026
MediumRoads

Monroe Street lighting improvements

The city is acquiring land from nine property owners for the roundabout project; the first three parcels were approved. Baldwin receives $10,390 and the Duffeys $300 for temporary construction easements.

2 mentionsLast discussed Oct 5, 2026
MediumRoads

Brint/Main/Holland-Sylvania roundabout right-of-way

The city is buying the eleven parcels needed for the next roundabout, using state safety funds — no city dollars spent on design so far. Council approved three acquisition-service contracts totaling about $150,000.

2 mentionsLast discussed Oct 5, 2026
MediumRoads

New bridge traffic concerns

Since the new bridge opened there have been accidents at the intersection; officials blame missing pavement markings, confusing signage, and desynchronized signals, and plan improvements before re-evaluating.

1 mentionLast discussed Sep 8, 2026
MediumRoads

Brint & Harroun Roundabout Right-of-Way

Council authorized two OPWC grant applications and completed land acquisition for the Erie/Monroe roundabout, including a $80,130 purchase from the Keevers and a $2,995 appropriation of the final parcel.

2 mentionsLast discussed Sep 8, 2026
MediumRoads

US-23/Monroe interchange construction and lighting gaps

The interchange stays on schedule, but the northbound off-ramp closes for 14 days starting May 29. Council approved $20,000 for Tetra Tech to design lighting the original ODOT contract missed on surface streets, with construction cost estimated at $50,000–$100,000 later.

1 mentionLast discussed May 18, 2026