Arlington Avenue Sewer Failure Phase II Loan
Summary
The sinkhole and multi-year sewer rebuild on Arlington Avenue continues into 2028, disrupting access, deliveries, and sales for local businesses — the backdrop for the proposed relief grant.
At a glance
- Total mentions
- 3
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 10, 2026.
Impact analysis
Business sales reportedly fall 40 to 80 percent during closures; the grant program would commit $25,000 in city funds.
The whole city benefits from the sewer repair; the grant targets affected storefront businesses.
Local storefront businesses losing customer access, deliveries, and revenue during years of construction.
Mentions & discussions (4)
City Council - Agenda Review for the Meeting of Toledo CIty Council - Nov 10, 2026
The sinkhole and multi-year sewer rebuild on Arlington Avenue continues into 2028, disrupting access, deliveries, and sales for local businesses — the backdrop for the proposed relief grant.
City Council - Agenda Review for the Meeting of Toledo City Council - Aug 18, 2026
The city is seeking a $16 million OWDA loan to fund Phase II repairs and replacements for a major sewer failure on Arlington Avenue. Residents have experienced severe basement backups during heavy rains.
City Council - Agenda Review for the Meeting of Toledo City Council - Apr 7, 2026
Severe wet weather required extra temporary pumps during ongoing repairs to a collapsed 48-inch sewer main on Arlington Avenue, increasing project costs by $2 million. Council reviewed a supplemental loan from the Ohio Water Development Authority to cover the unexpected expenses.
Arlington Ave.
Arlington Ave. City of Toledo (.gov)
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Toledo
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.