Summary
The $1.775 million contract with Perrin Asphalt covers repaving, sidewalks and curbs across Fire Department, Cornerstone/Independence, Belleau, Sandalwood, Gary, Presidential, Miktarian, Church, Edison and Darrow Road curbs, with alternate streets possibly following in 2027.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Jun 9, 2026.
Impact analysis
About $1.775 million from the fixed road program budget.
Drivers and pedestrians on the rescheduled streets get smoother roads, new sidewalks and repaired curbs.
Mentions & discussions (3)
City Council - Jun 9, 2026
Big construction season: Four Corners is basically done, roads are getting resurfaced, the Liberty Road trail starts this month, and Cannon Road hill work is finished.
City Council (Closed) - Mar 10, 2026
Two road projects moved forward: Perrin Asphalt won the Glenwood Drive job at $773,354.45 (first reading), and council adopted the ODOT agreement for Liberty Road resurfacing, which nets the city an extra 10% in funding. Also, Aero-Mark won the $136,145 2026 road striping contract.
City Council - Feb 10, 2026
The $1.775 million contract with Perrin Asphalt covers repaving, sidewalks and curbs across Fire Department, Cornerstone/Independence, Belleau, Sandalwood, Gary, Presidential, Miktarian, Church, Edison and Darrow Road curbs, with alternate streets possibly following in 2027.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Twinsburg
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.