Reed Road Water Park gutter repairs
Summary
Contractors fixing the 20-year-old pool's finish found failing concrete gutters. Council passed an emergency measure to fund complete repairs now while crews are already on site, keeping the pool open for summer and avoiding a costlier remobilization later.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Apr 13, 2026.
Impact analysis
Fits within the roughly $1 million Reed Road budget already set aside, with total identified repairs around $2 million and no full pool replacement needed.
Residents and families who swim and cool off at Reed Road Water Park this summer.