High PriorityDevelopmentopen

New Public Works Facility Construction

Summary

A new 14'x4' box culvert at 810 Northwoods Blvd will provide primary access to the new Public Works Facility. Council awarded the contract at $308,666 — about $118,000 under the engineer's estimate — though construction waits on federal permits.

At a glance

Total mentions
8
Last 30 days
0

Last discussed Sep 8, 2026.

Impact analysis

💰Financial impact

The contract comes in about $118,000 under the engineer's estimate of $426,362.50.

✅Who benefits

Residents gain improved city facilities and infrastructure delivered at a lower-than-expected cost.

Mentions & discussions (8)

MeetingSep 8, 2026

City Council (Regular) - Sep 8, 2026

A resident asked Council to name the new Public Works building after Lewis Thomas Hellard, who spent decades serving the city as an equipment operator, parks supervisor and assistant fire chief. The City has a formal naming process, which the Manager will share with Council.

MeetingAug 17, 2026discussed

City Council (Work) - Aug 17, 2026

Since 1988 the city has added 60+ lane miles but no more plow routes or supervisors; a new supervisor position is proposed for 2027, and the new public works building should be done by summer 2028.

MeetingJul 20, 2026

City Council (Work) - Jul 20, 2026

The big Public Works rebuild came in about $2.6 million under estimate. related contracts for security, inspections, lighting and electric service were previewed.

MeetingJul 20, 2026

City Council (Regular) - Jul 20, 2026

After years of being deferred, Vandalia is finally building a new Public Works facility. Council awarded the construction bid to Vancon, Inc. for about $14.9 million — roughly $2.6 million under the engineer's estimate — plus contracts for security systems and inspections.

MeetingJun 15, 2026discussed

City Council (Work) - Jun 15, 2026

The new $18 million Public Works Facility at 810 Northwoods Blvd. is fully designed and goes out for bid June 26, with awards targeted July 20 and completion by spring 2028.

MeetingApr 6, 2026

City Council (Regular) - Apr 6, 2026

A new 14'x4' box culvert at 810 Northwoods Blvd will provide primary access to the new Public Works Facility. Council awarded the contract at $308,666 — about $118,000 under the engineer's estimate — though construction waits on federal permits.

MeetingMar 16, 2026

City Council (Regular) - Mar 16, 2026

Council put about $18 million into the 2026 budget from the street, water, sewer and stormwater funds to build the new Public Works Facility, using bond anticipation notes issued in late 2025.

MeetingMar 16, 2026

City Council (Work) - Mar 16, 2026

The city is moving forward with an $18 million appropriation across street, stormwater, water and sewer funds to build the new Public Works Facility, paid for with bond anticipation notes issued in late 2025. A culvert providing primary access to the site also cleared bidding well under estimate.

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Vandalia

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.