Sanitary sewer overflow reduction design (Areas 6 and 8)
Summary
Council authorized up to $2 million in construction bidding and low-interest state loans (3.14%, 20-year) for the 2025 SSO reduction project, plus design work on the 2026 phase — EPA-mandated sewer improvements in areas 2, 3, 5, 7 and 10.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Jun 16, 2026.
Impact analysis
Up to $2 million in construction, financed through low-interest state loans rather than higher immediate costs.
Residents in sewer areas 2, 3, 5, 7 and 10 and the city, which avoids EPA penalties.
Mentions & discussions (3)
City Council - Jun 16, 2026
Council authorized design engineering for sewer overflow reduction in areas 6 and 8 — the first step toward fixing infrastructure that can cause sewage backups.
City Council - May 19, 2026
Council is moving ahead with hiring a designer to cut sanitary sewer overflows in two mapped areas — a budgeted 2026 project.
City Council - Jan 20, 2026
Council authorized up to $2 million in construction bidding and low-interest state loans (3.14%, 20-year) for the 2025 SSO reduction project, plus design work on the 2026 phase — EPA-mandated sewer improvements in areas 2, 3, 5, 7 and 10.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Wadsworth
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.