3 issues in roads with medium priority
ODOT project consent (Resolution 3905)
The Ohio Department of Transportation is providing technical assistance reviewing the city's transit operations. The update could point to recommended changes for how service is run.
Pedestrian hybrid beacon at Maple and Wooster
The pedestrian crossing beacon installed in 2025 was deactivated because its pole was too tall for drivers to see the activated lights. A correctly sized replacement pole is expected by end of November, then it goes back into service.
Capital projects pipeline 2026-2031
City Engineer Brad Holman laid out the full roads picture: 2026 paving done, the Brim Road path finished, Wallace water/sewer nearly complete, and a multi-year pipeline from the Krim-Scott Hamilton path to the North Main shared-use path in 2030-31.