HighRoads

Oakes Road Sidewalk Project Wrap-Up

The Safe Routes to Schools sidewalk project from Barr Road to Blossom Hill is moving forward with Allega as the low bidder at $268,808.85; work could start around May and finish before school resumes.

5 mentions (1 this month)Last discussed Nov 3, 2026
HighRoads

Valor Acres traffic studies

With two to three building sites left, the city is paying TMS Engineers $7,545 to independently verify the developer's traffic study assumptions, focused on Brecksville and Miller Road impacts.

4 mentions (2 this month)Last discussed Oct 20, 2026
HighRoads

Enbridge Utility Cuts on New Pavement

Enbridge is replacing old steel gas mains along Route 82, Wiese, Glen Valley, Calvin and Riverview down to Preston Village — a roughly four-month project affecting a couple hundred homes, with contractor appointments needed inside each house.

4 mentionsLast discussed Oct 6, 2026
HighRoads

Route 82 Sidewalk Grant Application

The city is applying for federal grant money through NOACA to build sidewalks on Chippewa Road (SR 82) from Cinnabar Drive to Riverview Road and make the Chippewa/Riverview intersection ADA-accessible. It's a funding application only — construction depends on getting the grant.

3 mentionsLast discussed Sep 15, 2026
HighRoads

Stop-sign and crosswalk safety at Sunnydale/Mill Road

Residents report cars running the three-way stop and crosswalk at Sunnydale and Mill Road, plus Mill/Hilton/Whitewood — right before school starts.

1 mentionLast discussed Aug 18, 2026
HighRoads

2026 Concrete Road Program Change Order

A big year for paving: all of Cambridge Village, Pershing Drive, Amber Lane, Winding Way, Valleybrook, Grenadier Lane, Riverview Road down to the Vaughn Road Bridge, and concrete replacement starting with Dunbar Lane in Bradford Village — plus 13,000 square feet of sidewalk work.

3 mentionsLast discussed Aug 18, 2026
HighRoads

Upcoming roadway and water main construction

Nearly every road will see work in the next couple of months: the Wallings Road bridge (targeting August 14), Mill Road one-way traffic, and water main work touching Brecksville and Sprague Roads. Closure lists go out via website, bulletin and email.

4 mentionsLast discussed Jul 21, 2026
HighRoads

Regional Transit Authority bus routes

RTA wants to run the 77 bus all the way to the southern city line instead of turning at Snowville Road, where about 18-19 riders a day already walk. It hinges on the new Allega Way intersection in Richfield opening, with an August 2026 start possible after a public hearing.

2 mentionsLast discussed Jan 20, 2026