Columbia Gas North Columbus High Pressure pipeline project
Columbia Gas will replace about 4.33 miles of pipeline in Gahanna during 2027, hitting Agler, James, Price, Morrison, North Hamilton, Taylor and Taylor Station roads. Expect about 60 days of significant traffic impacts on Taylor Road starting in January, though Taylor Station Road won't close.
New residential waste collection contract (Rumpke, 2027-2031)
Council picked Rumpke over incumbent Local Waste Services for the next residential trash and recycling contract, 6-1. Critics worry Rumpke could become the region's only provider, killing future competition.
West Side utility relief sewer and West Johnstown Road improvements
A relief sewer now about 30% designed will address water-in-basement problems from Coronation down through the College Park neighborhood, bundled with West Johnstown Road road improvements. The city will keep applying for federal BUILD grant money after missing this cycle.
Taylor Road Water Main Replacement cost increase
Construction ran into unexpected utility conflicts, so the engineer of record needs $64,032 more to keep verifying the work. It protects the design intent and public safety.
Rising electric aggregation rates
Gahanna Energy Plus has saved residents nearly $1 million, but SOPEC rates are climbing in the new term thanks to grid capacity shortages, data center demand, and global energy pressures. Residents can opt out during a 21-day window with no penalty, and officials suggest waiting for AEP's new price-to-compare before deciding.