35 issues with high priority
Water Treatment Plant High-Rate Study
An Ohio EPA-driven project to squeeze more water-making capacity out of the existing plant without a full rebuild — phases continue in 2027 and 2028 using low-interest state loans.
Electric, water and sewer rate increases
If council passes the three ordinances at the next meeting, a typical household's utility bill goes up about $17.27 a month (roughly $207 a year): water up 28%, electric up 5%, sewer up 8.5%. Officials say Wadsworth rates would still be about 12% below neighboring communities, and the revenue covers operations, capital and debt covenants since utilities run entirely on user fees.
Wadsworth Township fire and EMS contract
The township pays the city just over $537,000 a year, but the city kicks back 80% of EMS fees collected from township residents. Negotiations to raise the township's share are ongoing, and officials expect a deal within a manageable margin of the projections.
2027 City Budget
The city's 2027 tax budget projects flat income tax revenue and a preliminary $2.2 million General Fund deficit, though officials called it a conservative planning snapshot, not a real crisis. Income tax receipts are down about 5% this year after a record 2025.
Leaf Pick-up Schedule
Wadsworth just released its fall leaf pick-up schedule, so if you’ve got trees, check when to rake piles to the curb. Miss your date and you may be stuck bagging leaves or waiting for another option.
WCTV funding and future
A WCTV producer warned the community TV station is down to one employee after three departures in ten months and asked council what the station's future looks like.
Utility rate increases across water, sewer, electric and stormwater
Water rates jump 30%, sewer 8.5%, electric 5%, and stormwater goes from $4.50 to $5 a month. Even with the increases, Wadsworth households still pay roughly $80-95 less per month than neighbors in Brunswick or Medina.
Downtown infrastructure project moves forward
Main Street shop owners are worried the downtown project will clobber their holiday season — their most profitable months — and complain they got almost no notice before the southwest parking lot work started. The city says communication and business access are priorities but admits it can't dictate a contractor's schedule without risking delay damages.
Wadsworth Township fire/EMS contract (2027-2031)
The new five-year deal raises township payments 2% a year but ends the 80% EMS billing credit back to the township — netting the city about $265,000 for EMS needs. In exchange, township residents get billed at the lower city rate, which staff said barely matters since most are Medicare/Medicaid patients.
Growing EMS demand and staffing pressures
EMS calls hit a record 3,200 in 2025 and are running 6% above that. Part-time firefighter hiring is getting harder statewide, pushing the department toward more full-time staff — the core reason the EMS levy needs boosting.
2027 Police Department Budget
Police get a 4% raise (final year of the contract), with big lines for training, Cellebrite phone forensics, Flock cameras (~$36,000), body camera storage, and mental health check-ins for officers now paid from the general fund after grant funding ended. Rifle optics, steel range targets, drone software and suppressors would come from the law enforcement trust fund.
Rezoning five parcels to R-2 residential
The hotly contested Ordinance 26-090 rezones five city lots to R-2 residential, passing 4-3 after five readings.
MARCS emergency radio tower and FAA review
The city wants to build a 180-foot emergency radio tower on Oak Street to fix dead zones and let first responders talk directly to mutual aid partners. The FAA initially flagged it for poking into the airport's height-protection zone, and council's resolution asks the FAA to keep studying it — support letters are due October 17.
2027 Capital Projects Program
The city rolled out its proposed 2027 capital budget — roughly 31 major projects spanning utilities, roads, the airport, and downtown. Council will keep hashing this out in subcommittees through the fall before approving anything.
College Street rezoning to R-2 (Amended Ordinance 26-062)
A proposal to rezone two lots from R-1 to R-2 residential heads to a June 16 public hearing — neighbors will get their say.
ODOT resurfacing of State Route 94
The city's worst intersection gets a roundabout, mostly paid for by a $2 million NOACA grant plus low-interest state loans and TIF money. Construction expected spring through fall 2028, about 120 days of work.
Quadral Drive reconstruction
Council learned the Quadrel Drive rebuild could cost $3-4 million — far more than expected and not in the capital plan — and that the road fund cash being diverted downtown is money that could have gone there.
Redwood LLC rezoning and proposed apartment development
Redwood wants to rezone five parcels near SR 261 and the Speedway to R-2 for 111 apartment homes. Residents worry about traffic at the 261/Medina Line Road intersection and losing commercial land; the landowner says the site has sat unsold for two decades. Council hasn't voted yet — the ordinance moves to fifth reading.
City financial housekeeping and payroll system risk
Interim Auditor Jim Renacci warned the 25-year-old payroll system could fail (fixes quoted around $45,000/year), asked for a ~$5 million fund reallocation, flagged a broken customer-deposit ledger, empty airport hangars costing $85–95K a year, and utility collection software gaps behind $1.6 million in delinquencies.
Shadow Creek Planned Unit Development
The rezoning of lots 10232-10235 to the Shadow Creek Planned Unit Development advances to fourth reading, with a public hearing April 7 at 6:30 p.m. where residents can weigh in.
Employee health insurance renewal planning
The annual renewal with the Ohio Government Benefits Cooperative is moving forward; employee contribution details will come in a separate ordinance, with a possible special meeting next week.
Downtown stormwater improvements on Mills and Pardee Streets
Council adopted emergency legislation to bid out the first stormwater phase of the downtown infrastructure project — about $1.4 million — aiming to finish before year-end. Streets will stay open except for brief temporary closures.
Fifteen-year capital improvement plan
A $1.55 million addition to the capital improvement fund went down 3-4 after questions about how it fits with previously approved borrowing. This could delay capital projects until the issue is revisited.
$1.65 Million in Past-due Utility Bills
Council adopted a resolution telling the administration to build a plan for collecting utility bills that have gone past the point of service shutoff — and to decide what old bad debt should be written off.
Frontier Communications fiber oversight
About 5,300 homes are now service-ready on the city's fiber network, and extra crews are being added to speed up splicing. Council adopted the emergency materials purchase to dodge expected supply-chain delays.
Anthem proposal's hidden $1.2 million contract risk
Anthem's quote looked cheaper, but its stop-loss contract covered claims for only 12 months instead of the city's current 18 — an estimated $1.2 million gap if a major claim like a premature birth came in late. Anthem also projected claims falling 17%, which the consultant called unrealistic.
Westchester-area rezoning rejected
Council rejected the R-1 to R-2 rezoning of lots across from the Westchester Allotment after residents raised traffic congestion and property-value concerns.
Debt service payment on 2025 notes
Council members clashed over how much debt is too much — general fund debt service sits at 11.5% of income tax revenue and would hit 12.2% with the downtown add-on. Credit ratings start suffering above 15%. Officials promised a plan showing how debt comes back down as old loans retire.
Resident proposal to modernize traffic-impact ordinance
Residents urged Council to adopt a comprehensive transportation plan, noting roughly 700 new housing units near I-76 have been approved without any study of their combined traffic impact — and no citywide plan exists.
Wall Road Development annexation (94.2835 acres)
A developer wants to annex land south of the Brickyard project on Wall Road, needing rezoning and possibly TIF-backed infrastructure. A work session with the developer's presentation is planned for early March.
Sanitary sewer overflow reduction design (Areas 6 and 8)
Council authorized up to $2 million in construction bidding and low-interest state loans (3.14%, 20-year) for the 2025 SSO reduction project, plus design work on the 2026 phase — EPA-mandated sewer improvements in areas 2, 3, 5, 7 and 10.
Allegations regarding police evidence handling
A retired police officer told Council the police department pursued charges against him based on statements from a teen he says was known to be lying, and that evidence seized in his federal case left the evidence room and reached his children's school. Council took no action; a Norton PD investigation is reportedly under way.
City Auditor Retirement
Wadsworth’s city auditor is retiring after nearly 14 years, so the city needs to find a replacement soon. Why care? That office tracks the city’s money, so a smooth handoff matters for budgets, audits, and public trust.
Parking Code Change
Wadsworth rewrote its residential parking rules after a single complaint about a parked trailer. If you keep a boat, RV, or trailer on your driveway, where it can sit may have just changed—so check the new rules before you get a citation.
Downtown parking shortage
With a new 900-seat venue drawing crowds, two business owners asked whether the city has any plan to add downtown parking — no answer was given at the meeting.