S.R. 63 corridor access management and W. Main St. driveway relocation
The city planned to trade land with Mathers Mill Club, LLC — buying right-of-way for the S.R. 63 widening for $79,318 and selling an adjacent city parcel for the same amount. It's a step toward widening a busy state route.
Glosser Road roundabout progress
The Cincinnati/Glosser roundabout was expected to open the morning after the meeting, about two weeks early; the south leg has a design error to fix.
2026 Supplemental Street Paving
The final surface course of asphalt and striping goes down on North Broadway starting next week, with lane disruptions but no road closure.
Suncrest/Meadow Lane reconstruction
A $1.99 million project rebuilding Suncrest Lane and Meadow Drive — storm sewers, water mains, sanitary sewer work through Colonial Park West, new curbs, pavement, and sidewalks. A state grant is helping pay for it, and work starts in July.
Greentree Road roundabout construction
The Greentree Road improvement project has reached the Cincinnati Avenue intersection, which is now closed for roundabout construction with a posted detour; completion expected by late July. The intersection has a history of serious crashes.