Civic Issues
Topics getting the most attention in Perrysburg public meetings, ranked by how frequently they are discussed.
24 issues in water utilities
New water and sewer rates
Council passed ordinances setting new sanitary sewer and water rates — utility bills will change for residents and businesses.
Sanitary Sewer Credits
A homeowner spent nearly $2,000 excavating his yard after city technicians said a leak was on his side of the supply valve — but no leak was ever found. The city declined reimbursement, citing consistent treatment of all such cases, and the committee agreed to monitor the site and revisit the issue.
Water and Sewer Rate Increases
Your water and sewer bills would rise 2% a year for five years — about $1.17 more per month for a minimum-use household next year. The money funds EPA-mandated water main replacements, lead service line work, and a sewer overhaul projected near $100 million over 20 years.
Meter reader device replacement (MIUs)
The city is replacing aging radio-read water meter devices before they fail en masse. The $60,000 purchase of 500 units goes to Council next week since NECO is a sole-source supplier.
Watermain Replacement Project
Two 60-year-old pressure sustaining valves at the reservoirs are being replaced for up to $90,349 to keep water pressure reliable.
Wastewater plant digester project on track
A digester membrane at the wastewater plant failed catastrophically Friday afternoon, releasing methane. Staff worked around the clock through Tuesday with fire department and vendor support to contain it — a reminder of what keeps your water bills and services running.
Watermain replacement on Front, Second, Third and Indiana
The city is replacing waterlines on several near-downtown streets using directional drilling where possible to save trees, sidewalks, and driveways. The low bid came in under the $3.5M budget.
Front, Second and Third Street watermain improvements
Council reauthorized the state revolving loan agreement for the watermain replacement so the project can proceed.
Stormwater Fee Start-Up
Council finalized new stormwater management rules, set the utility base rate, and started a $1,500-per-acre pollution prevention deposit fund for construction sites.
Water main replacement on Front, Second, Third Streets
About 10,400 feet of water main in the northwest part of the city gets replaced this fall using directional drilling. An open house is planned so homeowners can get one-on-one answers before construction starts.
Stormwater utility launching January 2027
A new stormwater ordinance and resolution establishing the base rate got first readings — the $6 monthly rate starts January 1, 2027 and funds flood-control projects, with credits available for businesses and schools.
Wastewater treatment plant primary clarification expansion
A $484,500 design and bidding services contract with Fishbeck would move the wastewater plant expansion forward.
Stormwater utility fee outreach
Council took second readings of the stormwater management code overhaul and the resolution setting the stormwater utility base rate; votes come at the next meeting.
Wastewater plant primary clarification expansion
A new 66-foot primary clarifier tank, a duplicate of the existing one, will add about 6.3 million gallons of treatment capacity at the wastewater plant.
Ft. Meigs Ditch Repair and Multi-Use Path
An open house on January 21 showcased drawings and engineers for the multi-use path along the Fort Meigs Ditch — a chance for residents to weigh in before construction planning advances.
SSO Elimination Plan and Ohio EPA DFFO Compliance
Perrysburg's membership in the regional Stormwater Coalition helps the city meet federal MS4 stormwater permit education requirements — that's the source of those 'pick up after your dog' commercials under the 'Lake Erie Starts Here' campaign.
New DPU Office Manager Position
The city is adding an office manager for Public Utilities to oversee billing specialists and daily office operations, funded through the budget for a 2026 start. It should free up the director and deputy director for supervisory work and speed up hiring once Council signs off.
Water ordinance revisions — new pipe materials and 1-inch service lines
The city wants to allow materials other than copper for water service lines and bump the default size from 3/4-inch to 1 inch, which should cut costs and speed up connections. It's headed to Council with a request for a single reading.
Senior Loft Watermain Extension and W. 6th Street Fire Protection
A converted garage home set unusually far back on a narrow lot has no rear yard, so the owner needs variances for a front-yard shed and a side-yard pergola-style carport. A next-door neighbor spoke in favor.
Stormwater Utility Program Enterprise Fund
The stormwater advisory committee is considering $8/month for residents and $6/month for businesses, with an open house planned and possible start January 1, 2027. Legislation comes in March.
Reservoir pressure valve replacement
Two 60-plus-year-old valves that keep water pressure right at the city's reservoirs are failing — one is already dead. Council will decide on replacements to protect the water distribution system.
Natural gas aggregation extension with Archer Energy
The Archer Energy contract for residents and small businesses is extended for 23 months at a lower rate than previously discussed — approved as an emergency.
Wastewater plant influent screen rebuild
Two contracts totaling about $236,000 will rebuild the wastewater treatment plant's influent screen — unglamorous but essential to keep the plant running.
Storm Water Pollution Prevention Deposit Fund
Council created a new state-approved deposit fund to hold payments required when a stormwater pollution prevention plan is needed; any money not spent on completing the plan goes back to the property owner or developer.